ITB Revitalization News

Painting Progression

Painting continues. We are nearing the end of Phase 2 and will be transitioning into Phase 3 next week (week of September 19).

Painting – currently

The painters are currently working on vacant offices on the 3rd floor. Next they will begin work on the 1st floor vacant rooms, and then move on to the 2nd floor unoccupied rooms.